The Takoma Metro Lot Has Its Zoning Approval. What It Still Needs Is Financing.

For most of its history, the surface lot beside the Takoma Metro station was stuck on one question: what should be built there? Neighbors, zoning rules and Metro's board took about two decades to settle it. The plan is now settled. The DC Zoning Commission gave its approval in 2024. On September 24, 2026, it voted 5-0-0 to give the project two more years. The development team asked for that time because it couldn't get the project financed.

That's a new kind of delay for this site. Plenty of people expected the lot to stay a lot through 2026, but this time the reason has changed.

A Lot That Took Twenty Years to Get to Yes

WMATA's own board record goes back to the early 2000s for this 6.8-acre property. Most of the delays it records are about what the site was allowed to become.

Year What happened at the Takoma station lot
2005 Metro's board approves a joint development agreement with EYA
After 2008 Community opposition and the post-crisis economy stall the original proposal
2014 Metro's board approves an amended agreement with EYA for a revised plan
2021 The project is on hold over zoning ambiguity and community feedback until the DC Council adopts a Comprehensive Plan update that allows more development
January 17, 2023 Metro holds a Compact Public Hearing on the transit changes
May 11, 2023 Metro's board approves moving the bus loop and cutting Kiss & Ride to 16 spaces
2023 DC's Historic Preservation Review Board signs off on the design
2024 The Zoning Commission order approving the project takes effect July 26, 2024
May 2025 A Metro board committee takes up a second amended agreement, with groundbreaking expected in winter 2026

Before 2021, the pauses came from community opposition, the economy after 2008, and unclear zoning for the site. The 2021 Comprehensive Plan update settled the rules. EYA then changed the plan to add more housing and a larger public park. The historic preservation, transit and zoning reviews all came in the three years after that.

What the Approved Plan Would Put Between Carroll Street and Eastern Avenue

The Zoning Commission's case record describes the site this way: Metrorail tracks on the west, Carroll Street NW on the south, Cedar Street NW on the east, Eastern Avenue NW on the northeast. It falls within ANC 4B04. The DC Office of Planning's September 11, 2026 report summarizes what was approved.

  • A 76-foot mixed-use building with 434 homes
  • 15 percent of those homes set aside as inclusionary zoning units for households at 30 and 60 percent of area median income
  • Between 15,000 and 18,000 square feet of retail and service space
  • 1.8 acres of public open space

According to UrbanTurf's July report, the open space would be split between a park along Eastern Avenue and a retail plaza. Moya Design Partners designed the project. The affordable homes include six three-bedroom units.

The plan would also change how the station works. Under the agreement, Metro would sell the land outright. The developer would rebuild the bus loop, a smaller Kiss & Ride, a break room for bus operators and new bike facilities. Metro's 2023 approval moves the bus loop, adds one drop-off stop and reduces Kiss & Ride to 16 spaces. So bus riders, drivers dropping someone off and cyclists would all feel the change at the station, along with whoever lives in the new building.

Where the Schedule Broke

In May 2025, Metro's board document set out the next steps with confidence:

"Next steps include design, permitting, closing and construction of the proposed development with groundbreaking anticipated in winter 2026."

That line is from the WMATA board document taken up by its finance committee on May 15, 2025. Fourteen months later, the plan hadn't changed, but the cost of building it had.

In a filing dated July 20, 2026, the development team, TM Associates LLC (an EYA affiliate) and WMATA, told the Zoning Commission it could not secure financing. It cited higher interest rates, construction costs, insurance premiums and operating expenses. It also said construction loans and equity investment had become harder to get. UrbanTurf reported that the affordable housing component was part of the financing challenge.

The filing also says that neither the approved plan nor a version with a larger share of affordable homes could be financed under current conditions. That's the main reason the lot is still empty. Changing the design or the unit mix doesn't solve it. When the site's earlier proposals stalled, the usual fix was to revise the plan. This time, the filing says neither plan works financially.

The September 24 Vote

The Zoning Commission's original order took effect July 26, 2024, and was set to expire July 26, 2026. It had never been extended. The team asked for two more years, and the Office of Planning recommended approval, moving the expiration to July 26, 2028. At its September 24 meeting, the Commission voted 5-0-0 to approve the extension in Case 22-36A. The case remains listed as active.

The applicant said it needs the extra time to secure financing and file for a building permit. It also said it has met with the Deputy Mayor for Planning and Economic Development, the Department of Housing and Community Development and DC Council representatives to look for legislative and financing tools that could help. Each of those meetings is about how to pay for the project.

What to Watch Between Now and July 2028

The zoning and design approvals are done, so the next signs of progress will come from finance and permitting. Based on the public record, these are the steps to follow, roughly in order:

  1. A financing tool from the District. The applicant has asked DMPED, DHCD and the Council for help, so any new subsidy or legislation for the project would likely come from that work.
  2. A building permit application. The applicant named this step as what the two extra years are for.
  3. The land sale closing. Metro's agreement calls for selling the land outright, and closing comes after design and permitting in Metro's own list of next steps.
  4. Work on the bus loop and Kiss & Ride. Since the developer has to rebuild those facilities, construction near the station entrance would be among the first visible changes.

The case is listed under the Zoning Commission's Case 22-36A page, and new filings will appear in its record.

A Few Blocks Over, Another Long Wait That Did End

Takoma has seen a long-delayed project finish before. The Takoma Theatre at 6833 4th Street NW was vacant when it was bought in 2015. A 2018 Main Street Takoma announcement said Children's National and two food tenants would move into the restored building. Lost Sock Roasters had aimed to open its café there in late 2019. Daily Coffee News reported that it opened in early February 2021. Today, Children's National lists the building as a pediatric neurology and behavioral health location. Lost Sock and Turning Natural are listed as its on-site food businesses, and Lost Sock's coffee bar is listed as open Tuesday through Friday, 7 a.m. to 4 p.m.

The next public event on that block is coming up soon. Main Street Takoma lists Pajamarama for Sunday, December 6, 2026. Shoppers who come in pajamas get early discounts at participating businesses from 8 to 11 a.m. From 10 a.m. to 3 p.m., Lost Sock hosts an outdoor holiday market of local artists, makers and collectors beside the theatre. The Jammie Jam runs from 10:30 a.m. to 1:30 p.m. at the School of Musical Traditions, 7112 Willow Avenue.

If you own near the Takoma station and want to know how a 2028 timeline for the lot could factor into your plans, The MAC Group follows Case 22-36A closely and is glad to walk through it with you. Contact Us.